Question

Aptitude Questions:

12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

  • 45 days
  • 48 days
  • 50 days
  • 54 days
  • None of these
Answer- B

As per formula, m1d1 = m2d2

=>  12 x 16 = 4 x d2

=> d2 = 48